• New England Boring Contractors will be conducting Geotechnical boring work at five
locations along the low-lying roads stretching from Pole Dike Rd. and Bound Brook Island
Rd. in Wellfleet, North to Lombard Hollow along Old County Rd in South Truro.
 
• This work, while originally scheduled to take place the week of February 19th, has been
rescheduled to take place the week of February 26th. The contractor anticipates
conducting one boring per day for a total of five days of work 2/26/24 through 3/1/24.
 
• The contractor anticipates staging their drill rig in a fashion that will permit one lane of
traffic around the drilling operations. In the event that this is not feasible, a detour route
will be established for traffic. A police detail will be present to assist with traffic
management.
 
Additional information can be found at www.herringriver.org