FY 27 Capital Budget

  FY 2026FY2027FY2028FY2029FY2030FY2031
Department AssestAmount Amount AmountAmount Amount Amount 
General Government       
Town Hall Exterior Repairs   $220,000   
 Repair/Maintenance Program$75,000$50,000 (free cash)$75,000$75,000$75,000$75,000
 ADA Replacement/Upgrade Program$0$35,000 (free cash)$35,000$35,000$35,000$35,000
Sub-Total  $75,000$85,000$330,000$110,000$110,000$110,000
Maurice's Maurice's Campground Site Development $225,000$0$225,000$225,000$225,000$225,000
Sub-Total  $225,000$0$225,000$225,000$225,000$225,000
Info Technology IT Network Replacement Program $39,000$39,000 (free cash)$39,000$39,000$39,000$39,000
 Meeting Connectivity $30,000 (free cash)    
 IT PC & Components Replacement Program $40,000$40,000 (free cash)$45,000$50,000$50,000$50,000
Sub-Total $79,000$109,000$84,000$89,000$89,000$89,000
Shellfish Floating Upweller Nursery    $45,000  
 Fleet Replacement Program$32,000$32,000 (RR)$32,000$32,000$32,000$32,000
 Work Boat (Skiff)  $35,000$35,000  
 Engine/Equipment Replacement Program$6,000$6,000 (RR)$20,000$6,000$6,000$6,000
Sub-Total $38,000$38,000$87,000$118,000$38,000$38,000
TOTAL GENERAL GOVERNMENT $417,000$232,000$726,000$542,000$462,000$462,000
Public Safety        
PoliceHvac Upgrade  $150,000   
 Police Repair/Maintenance Program$50,000$40,000 (free cash)$50,000$50,000$50,000$50,000
 Fleet Replacement Program$152,000$152,000 (free cash)$152,000$152,000$152,000$152,000
 Deprtment Equipment Replacement $43,500$38,500 (free cash)$43,500$43,500$43,500$43,500
 Interior Furnishings (desk-chairs-table-storage)  $15,000 (free cash)  $65,000 
Sub-Total  $245,500$245,500$395,500$245,500$310,500$245,500
Dispatch Dispatch Equipment Replacement Program$5,000$5,000 (free cash)$5,000$5,000$5,000$5,000
 Security Camera System$23,000     
 CAD Software Upgrade $200,000 (borrow)    
Sub-Total $28,000$205,000$5,000$5,000$5,000$5,000
Fire       
 Fire Repair/Maintenance Program $50,000$50,000 (free cash)$50,000$50,000$50,000$50,000
 Ambulance 97 Replacement $303,700     
 Ambulance 98 Replacement   $600,000   
 Ambulance 99 Replacement    $600,000  
 Forrestry Trcuk 90   $350,000   
 Fleet replacement Program$33,000$33,000 (free cash)$33,000$33,000$30,000$30,000
 Rigid Hull Inflatable Boat    $75,000  
 Medical Rescue Equipment Replacement $35,500$35,500 (RR)$35,500$35,000$35,000$35,000
 Fire Suppression System Replacement Program$29,000$29,000 (free cash)$29,000$29,000$29,000$29,000
 Radio Communication Equipment Replacement Program$19,000$19,000 (free cash)$19,000$19,000$19,000$19,000
 SCBA Compressor System  $100,000 (free cash)    
Sub-Total $516,500$266,500$1,116,500$841,000$163,000$163,000
TOTAL PUBLIC SAFETY  $790,000$717,000$1,517,000$1,091,500$478,500$413,500
Education WES Boiler Repairs   $1,000,000$1,000,000  
 WES Repair/Maintenance Program$75,000$75,000 (free cash)$75,000$75,000$75,000$75,000
 School Equipment/Furnishing Replacement Program$15,,500$15,500 (free cash) $15,500$15,500$15,500$15,500
TOTAL EDUCATION $90,500$90,500$1,090,500$1,090,500$90,500$90,500
Public Works DPW Facilities Repair/Maintenance Program $50,000$40,000 (free cash)$50,000$50,000$50,000$50,000
 Fuel Rank Replacment   $100,000   
 Maguires Landing $0     
 White Crest Beach Landing   $400,000   
 Newcomb Hollow Beach Landing   $400,000   
 Gull Pond Beach Landing $3,500 $225,000   
 Long Pond Beach Landing $5,000     
 Kelliers Corner Reventment & Stormwater Improvement $125,000 (grant match)    
 Briar Lane Culvert  $125,000 (grant match)    
 Lt. Island Bridge  $50,000   
 Fleet Replacement Program$80,000$80,000 (free cash) $80,000$80,000$80,000$80,000
 Refuse Trailer$140,000     
 Gestalt HVAC $70,000 (free cash)    
 Interstate Trailer  $40,000   
 DPW Equipment Replacement Program$35,000$35,000 (free cash)$35,000$35,000$35,000$35,000
Sub-Total $313,500$475,000$1,380,000$315,000$165,000$165,00
Waste WaterPlanning, Permitting & Testing$320,000     
 Engineering & Design  $5,000,000   
 Implementation/Construction   $50,000,000  
 Enhanced IA Subsidies$360,000     
Sub-Total $680,000$0$5,000,000$50,000,000$0$0
Transfer Station Transfer Station Repair/Maintenance Program$25,000$20,000 (RR)$25,000$25,000$25,000$25,000
 Peterbuilt Tractor (to haul trash)    $100,000  
 Transfer Station Equipment Replacement Program $22,000$22,000 (RR)$22,000$22,000$22,000$22,000
 Transfer Station Scale $115,000 (RR)    
 Transfer Station Compactor 1   $53,000  
 Transfer Station Compactor 2  $50,000   
 Transfer Station Compactor 3    $55,000 
 Trasnfer Station Compactor 4 (new recycling)$30,000     
Sub-Total $77,000$157,000$97,000$200,000$102,000$47,000
Road Repairs Local Road IMprovement Program$75,000$75,000 (chpt. 90)$75,000 (chpt. 90) $75,000 (chpt. 90) $75,000 (chpt. 90) $75,000 (chpt 90)
 6 Wheel Truck $200,000 (chpt. 90)     
 10 Wheeler    $500,000 
Sub-Total $75,000$275,000$75,000$75,000$575,000$75,000
TOTAL PUBLIC WORKS $1,145,500$907,000$6,552,000$50,590,000$842,000$287,000
Human Services Fleet Replacement Program$9,000$64,000 (free cash)$9,000$9,000$9,000$9,000
COAKitchen Equipment Replacement Program $1,200$1,200 (free cash)$1,200$1,200$1,200$1,200
 Equipment Replacement Program $3,500$3,500 (free cash) $3,500$3,500$3,500$3,500
 COA Windows and Doors  $200,000   
 COA Repair/Maintenance Program$50,000$40,000 (free cash)$50,000$50,000$50,000$50,000
Sub-Total $63,700$108,700$263,700$63,700$63,700$63,700
TOTAL HUMAN SERVICES $63,700$108,700$263,700$63,700$63.700$63,700
Culture & Recreation        
Library Engining/Design Library Improvement  $500,000   
 Fire Suppression System   $2,000,000  
 Video Studio Renovation   $2,000,000  
 Library Repair/Maintenance Program$25,000$25,000 (free cash)$25,000$25,000$25,000$25,000
 Furniture and Shelving Replacement Program $5,000$5,000 (free cash) $5,000$5,000$5,000$5,000
 Technology Upgrades$0     
Sub-Total $30,000$30,000$530,000$4,030,000$30,000$30,000
RecreationRecreation Equipment Replacement Program$9,000$9,000 (RR)$9,000$9,000$9,000$9,000
 Court Resurfacing$10,750$10,750 (RR)$10,750$10,750$10,750$10,750
 Skateboard Park$20,000$6,500 (RR)$6,500$6,500$6,500$6,500
 Baseball Court Lighting    $25,000  
 Skateboard Park Lighting   $25,000   
 Tennis/Pickleball Lighting     $30,000 
 Skateboard Park Ramp $42,000 (RR)$60,000   
 Vegetative Windscreen for courts$15,000     
 Changing Room Structure $10,000     
 Baker's Field Upgrades   $800,000  
 Baker's Field Repair/Maintenance Prgram$10,000$10,000 (RR)$10,000$10,000$10,000$10,000
 Transportation Van 2     $65,000
 Bleachers for WES Ballfield $10,000 (RR)    
Sub-Total $74,750$88,250$121,250$861,250$66,250$101,250
BeachFleet Replacement Program$11,500$11,500 (RR) $11,500$11,500$11,500$11,500
 Equipment Replacement Program$7,500$7,500 (RR)$7,500$7,500$7,500$7,500
 Supplemental Equipment - Life Guard Stands $53,500     
Sub-Total $72,500$19,000$19,000$19,000$19,000$19,000
TOTAL CULTURE & RECREATION $187,250$137,250$670,250$4,910,250$115,250$150,250
TOTAL GENERAL FUND $2,673,950$2,192,450$12,382,450$59,379,450$2,051,950$1,466,950
        
Water EnterpriseSystem Development & Planning $50,000$45,500 (RE)$12,800   
 Water Tank Maintenance $240,000 (borrow)    
 Treatment Facilitites Maintenance/Upgrades$15,000   $44,500 
 Well & Pump Station Maintenance/Upgrades $37,500 (RE)$37,500$17,500  
TOTAL WATER ENTERPRISE $65,000$323,000$50,300$17,500$44,500 
        
Marina EnterpriseHarbor Building Repair/Maintenance Program$50,000     
 Marina Facility Repair/Maintenance Program$10,000$10,000 (RE)$10,000$10,000$10,000$10,000
 Timber Bulkhead Repari/Maintenance Program$5,000$5,000 (RE)    
 Electrical Code Compliance $50,000$50,000 (RE)$50,000$50,000$50,000$50,000
 Marina Fleet Replacement $260,000$50,000 (RE)$100,000$100,000$100,000 
 L-Pier Replacement  $200,000 (borrow) $7,000,000$100,000 
 Area 1 Dredging (Pier/inner Channel Permit & Mitigation  $4,250,000   
 Maintenance Dredge $500,000 (borrow)    
 Area 2 Dredging (Mooring Field Permit & Mitigation)$250,000 $4,250,000   
 Dredge  $3,000,000 $3,000,000 
 Docks and Pilings from Storm $680,000 (borrow/free cash)    
 Harbor Master Light Duty Vehicle$130,000     
 Medium Duty Vehicle  $70,000   
 Harbor Work Boat      $150,000
 Boat Engine Replacement Program $9,000$9,000 (RE)$9,000$9,000$9,000$9,000
 Equipment Trailer Replacement Program $3,500$3,500 (RE)$3,500$3,500$3,500$3,500
 Pier Camera System$15,000  $5,000  
TOTAL MARINA ENTERPRISE $782,500$1,327,500$7,492,500$10,877,500$3,272,500$172,500
        
GRAND TOTAL ALL FUNDS $3,521,450$3,842,950$19,925,250$70,724,450$5,368,950$1,639,450
   (Debt Deficit) $605,148    
   $4,448,098    
SOURCES FY27       

Free Cash

$1,379,700Free Cash Calculation      
Debt Deficit Free Cash$605,148$5,727,432Free Cash Certified     
Grant Match Free Cash$250,000$-2,234,848Total Free Cash for Capital     
Shellfish (RR)$38,000$3,492,584Subtotal of remaining Free Cash     
Ambulance (RR)$35,500-$350,000Stabilization    
Transfer Station (RR)$157,000-$400,000Capital Stabilization    
Recreation (RR)$88,250$2,742,584Free Cash Balance     
Beach (RR)$19,000      
Water (RE)$83,000      
Marina (RE)$127,500      
Chapter 90 $275,000      
Borrow$1,390,000      
TOTAL$4,448,098